Publicación: Conversión de la unidad viscorreductora II de la GRB en una unidad de coquizado retardado: análisis por simulación y evaluación del potencial económico
| dc.contributor.advisor | Morales Medina, Giovanni | |
| dc.contributor.author | Rodriguez Niño, Edward Leonardo | |
| dc.date.accessioned | 2024-03-04T00:09:01Z | |
| dc.date.available | 2018 | |
| dc.date.available | 2024-03-04T00:09:01Z | |
| dc.date.created | 2018 | |
| dc.date.issued | 2018 | |
| dc.description.abstract | Actualmente, la Gerencia Refinería Barrancabermeja (GRB) cuenta con un esquema de media conversión, generando un combustóleo comercial por dilución con aceite liviano de ciclo. La transformación de la GRB a una refinería de alta conversión conlleva el cambio de la Viscorreductora II por una unidad de coquizado retardado. En el presente trabajo se desarrolla un análisis del desempeño de una planta de coquizado retardado en la GRB, basado en resultados obtenidos por simulación. La metodología envuelve la validación, con datos históricos, de una simulación en Hysys para la unidad Viscorreductora II, una posterior simulación de una unidad de coquizado retardado basado en la redistribución de los equipos y el respectivo cálculo de los potenciales económicos. Los resultados de la simulación para la Viscorreductora II concuerdan con la generación de productos livianos resultantes del craqueo térmico medio de fondos. La simulación fue evaluada considerando datos históricos, por medio del Aspen Simulation Workbook mostrando una convergencia en el 53% de los casos, debido a fluctuaciones en las propiedades de la carga y a muestras en estado dinámico. Los flujos de gasóleo de los históricos fueron reproducidos por la simulación a partir del ajuste de la temperatura del horno; este ajuste fue necesario debido a la carencia de assays de la carga. La simulación de una unidad de coquizado retardado fue desarrollada a partir de la simulación anterior; los rendimientos másicos de productos livianos del coquizado correspondieron a ca. 63.5%. La comparación de resultados con las regresiones de Volk et al., conduce a afirmar que las tendencias de las simulaciones concuerdan con lo esperado para una unidad de coquizado retardado. Finalmente, el potencial económico de la unidad de coquizado retardado es superior que para la Viscorreductora II debido principalmente a la eliminación de la producción de combustóleo. | |
| dc.description.abstractenglish | Currently, the Gerencia Refinería Barrancabermeja (GRB) has a half conversion scheme, generating a commercial fuel oil N 6 by dilution with light cycle oil. The transformation of the GRB to a high conversion refinery entails the change of the Visbreaking-II unit by a delayed coking unit. In the present work an analysis of the performance of a delayed coking plant is developed, based on results obtained by simulation. The methodology involves the validation, with historical data, of a simulation in Hysys for the Visbreaking-II unit, a subsequent simulation of a delayed coking unit based on the redistribution of the equipment and the corresponding calculation of the economic potentials. The results of the simulation for the Visbreaking-II are consistent with the generation of light products resulting from the medium thermal cracking of bottoms. The simulation was evaluated considering historical data, by the application of the Aspen Simulation Workbook, showing a convergence in 53% of the cases, due to fluctuations in properties of the feed and samples in dynamic state. The historical gasoil flows were reproduced by the simulation from the adjustment of the furnace temperature; this adjustment was required due to the lack of feed assays. The simulation of a delayed coking unit was developed from the previous simulation; light coking products yielded ca. 63.5%wgt. The comparison of results with the regressions of Volk et al. leads to affirm that the trends of the simulations agree with what was expected for a delayed coking unit. Finally, the economic potential of the delayed coking unit is higher than for the Visbreaking-II due mainly to the elimination of fuel oil N 6 production. | |
| dc.description.degreelevel | Pregrado | |
| dc.description.degreename | Ingeniero Químico | |
| dc.format.mimetype | application/pdf | |
| dc.identifier.instname | Universidad Industrial de Santander | |
| dc.identifier.reponame | Universidad Industrial de Santander | |
| dc.identifier.repourl | https://noesis.uis.edu.co | |
| dc.identifier.uri | https://noesis.uis.edu.co/handle/20.500.14071/39062 | |
| dc.language.iso | spa | |
| dc.publisher | Universidad Industrial de Santander | |
| dc.publisher.faculty | Facultad de Ingenierías Fisicoquímicas | |
| dc.publisher.program | Ingeniería Química | |
| dc.publisher.school | Escuela de Ingeniería Química | |
| dc.rights | http://creativecommons.org/licenses/by/4.0/ | |
| dc.rights.accessrights | info:eu-repo/semantics/openAccess | |
| dc.rights.creativecommons | Atribución-NoComercial-SinDerivadas 4.0 Internacional (CC BY-NC-ND 4.0) | |
| dc.rights.license | Attribution-NonCommercial 4.0 International (CC BY-NC 4.0) | |
| dc.rights.uri | http://creativecommons.org/licenses/by-nc/4.0 | |
| dc.subject | Viscorreduccion | |
| dc.subject | Coquizado Retardado | |
| dc.subject | Simulación | |
| dc.subject | Severidad | |
| dc.subject | Rendimiento | |
| dc.subject | Assay | |
| dc.subject | Tbp | |
| dc.subject | Validación De Históricos. | |
| dc.subject.keyword | Viscorreduction | |
| dc.subject.keyword | Delayed Coking | |
| dc.subject.keyword | Simulation | |
| dc.subject.keyword | Severity | |
| dc.subject.keyword | Performance | |
| dc.subject.keyword | Assay | |
| dc.subject.keyword | Tbp | |
| dc.subject.keyword | Historical Validation. | |
| dc.title | Conversión de la unidad viscorreductora II de la GRB en una unidad de coquizado retardado: análisis por simulación y evaluación del potencial económico | |
| dc.title.english | Conversion of visbreaking-ii unit of the grb into a delayed coking unit: analysis by simulation and evaluation of the economic potential* | |
| dc.type.coar | http://purl.org/coar/version/c_b1a7d7d4d402bcce | |
| dc.type.hasversion | http://purl.org/coar/resource_type/c_7a1f | |
| dc.type.local | Tesis/Trabajo de grado - Monografía - Pregrado | |
| dspace.entity.type | Publication |
Archivos
Bloque original
1 - 3 de 3
Cargando...
- Nombre:
- Carta de autorización.pdf
- Tamaño:
- 338.59 KB
- Formato:
- Adobe Portable Document Format
Cargando...
- Nombre:
- Nota de proyecto.pdf
- Tamaño:
- 156.3 KB
- Formato:
- Adobe Portable Document Format