dc.descriptionThe peiformance 01the production 01type A plant is conditioned by the restrictive resources ofcapacity. These resources determine the production rhythm, making them the critical factor insolvingproblems re/ated to the units' excess, schedule ofproduction and the increase in thefinalpraduct cas!. This is why a procedure was established to protect and control the restrictions inthe production system in situations like, time variations in the production process at workstafions, Ihe dependence among them and Ihe murphy effeet that is presented during theproduefion. Thanks lo this procedure, it is possible to know the size of the time buffer whichguaranties thepermanent materialjlow, decrease in production stocks and improve the efficiencyofthe producfion system.en-US
dc.descriptionEl desempeño de una planta de producción tipo A se encuentra condicionado por los RecursosRestrictivos de Capacidad, éstos son los recursos que determinan el ritmo de producción, por lotanto se convierten en un punto crítico al momento de resolver problemas relacionados con elexceso de inventario, la programación de la producción y el aumento en el costo del productoterminado. Por esta razón se planteó una metodología, la cual permite controlar y proteger larestricción del sistema de producción de situaciones como por ejemplo, las variaciones deltiempo de procesamiento en las estaciones de trabajo, la dependencia entre ellas y el efectoMurphy que se presenta durante la producción. Con esta metodología se conoce el tamañofactible del Amortiguador de Tiempo, garantizando un flujo continuo de material, disminuciónel nivel de Inventario y mejorando la eficiencia en el sistema productivo.es-ES
dc.formatapplication/pdf
dc.identifierhttps://revistas.uis.edu.co/index.php/revistauisingenierias/article/view/2274
dc.identifier.urihttps://noesis.uis.edu.co/handle/20.500.14071/8176
dc.languagespa
dc.publisherUniversidad Industrial de Santanderes-ES
dc.relationhttps://revistas.uis.edu.co/index.php/revistauisingenierias/article/view/2274/2633
dc.rights.accessrightsinfo:eu-repo/semantics/openAccess
dc.rights.coarhttp://purl.org/coar/access_right/c_abf2
dc.rights.creativecommonsAtribución-NoComercial-SinDerivadas 4.0 Internacional (CC BY-NC-ND 4.0)
dc.rights.licenseAttribution-NonCommercial 4.0 International (CC BY-NC 4.0)
dc.sourceREVISTA UIS ENGENHARIAS; v. 3 n. 1 (2004): Revista UIS Ingenierías; 41-50pt-BR
dc.sourceRevista UIS Ingenierías; Vol. 3 Núm. 1 (2004): Revista UIS Ingenierías; 41-50es-ES
dc.sourceRevista UIS Ingenierías; Vol. 3 No. 1 (2004): Revista UIS Ingenierías; 41-50en-US
dc.source2145-8456
dc.source1657-4583
dc.subjectShock absorberen-US
dc.subjectrestrictionen-US
dc.subjectplanten-US
dc.subjectresaurce, variatians, murphy, Balanceen-US
dc.subjectresaurceen-US
dc.subjectvariatiansen-US
dc.subjectmurphyen-US
dc.subjectBalanceen-US
dc.subjectAmortiguadores-ES
dc.subjectrestricciónes-ES
dc.subjectplantaes-ES
dc.subjectrecursoes-ES
dc.subjectvariacioneses-ES
dc.subjectmurphyes-ES
dc.subjectbalanceoes-ES
dc.titleAmortiguadores de tiempo en una planta de producción tipo a: metodología para su obtención y análisises-ES
dc.titleTime dampers in a type a production plant: methodology for obtaining and analyzingen-US