Publicación: Identificación de tiempo pérdido invisible para la reducción de tiempo de construcción de pozos de un campo de Ecopetrol
| dc.contributor.advisor | Saavedra Trujillo, Nestor Fernando | |
| dc.contributor.advisor | Calderon Carrillo, Zuly Himelda | |
| dc.contributor.advisor | Mateus Tarazona, Darwin Clemente | |
| dc.contributor.author | Pinto Parada, Loreina Eliana | |
| dc.contributor.author | Navas Merchan, Sergio Andres | |
| dc.date.accessioned | 2024-03-03T23:29:54Z | |
| dc.date.available | 2017 | |
| dc.date.available | 2024-03-03T23:29:54Z | |
| dc.date.created | 2017 | |
| dc.date.issued | 2017 | |
| dc.description.abstract | El tiempo perdido invisible (ILT), es aquel tiempo que aparece dentro de lo que se conoce como tiempo productivo en los reportes diarios de perforación, sin embargo, no es del todo productivo. Este es afectado por el grado de eficiencia con que se logra ejecutar una actividad. El ILT ofrece la oportunidad de disminuir el tiempo de construcción de un pozo y, por ende, significar en un ahorro de capital para una Empresa. En este trabajo se presenta un estudio de tiempos productivos para algunas actividades en pozos de un campo de Ecopetrol, con el fin de identificar el ILT en las campañas 2015, 2016 y parte del 2017. Para establecer estos tiempos productivos de perforación y completamiento, se empieza por analizar los reportes diarios y compararlos entre sí. La comparación se puede realizar debido a que se tienen pozos perforados en una misma zona con características mecánicas similares. Posteriormente se elige un tiempo de referencia, para comparar los tiempos de los pozos. Este puede ser el mínimo o el promedio, que sirve para evidenciar un posible ILT. Estos valores quedarán como punto de referencia de desempeño y su elección dependerá de las exigencias de la empresa. El análisis que se mencionó anteriormente proporciona un tiempo perdido invisible, no obstante, no se puede reconocer el factor que causa este menor desempeño de un pozo respecto a otro; por ende, el siguiente paso es establecer las actividades que se llevaban a cabo con más frecuencia para la construcción de pozos. Por cada actividad seleccionada se escoge un tiempo de referencia y a partir de este valor se calcula el posible tiempo perdido invisible e igualmente se establece este valor como estándar de desempeño para futuros proyectos. Este valor debe ir en constante renovación con los proyectos nuevos que se ejecuten. | |
| dc.description.abstractenglish | Invisible lost time ILT, is the time that appears within what is known as productive time in the daily drilling reports, however, it is not productive in every sense. This is directly affected by the degree of efficiency with which is possible to run an activity. The invisible lost time offers the opportunity to reduce the construction time of a well, and therefore, means a capital saving for a company. This work presents a study of productive time for some activities in the wells of an Ecopetrol field, in order to identify ILT in the 2015, 2016 and part of the 2017 campaigns. To establish these productive times of drilling and cementation, it is needed to begin by analyzing the daily drilling reports of the wells and compare them together. The comparison can be performed since there are wells drilled in the same area with similar mechanical properties. Subsequently a reference time is chosen, to compare the times of other wells. This may be the minimum or average, which will help to demonstrate a possible ILT. These values will be a target for performance and its choice will depend on the requirements of the company. The analysis mentioned above provides an invisible lost time, however, it is not possible to recognize the factor that causes a low performance of one well with respect to another; Therefore, the next step is to establish activities that were carried out more frequently for the construction of each well. For each selected activity, a reference time is chosen, and, from this value, the possible invisible lost time is calculated, finally this value is set as a standard of performance for future projects. This value must be in constant renovation with new projects running. | |
| dc.description.degreelevel | Pregrado | |
| dc.description.degreename | Ingeniero de Petróleos | |
| dc.format.mimetype | application/pdf | |
| dc.identifier.instname | Universidad Industrial de Santander | |
| dc.identifier.reponame | Universidad Industrial de Santander | |
| dc.identifier.repourl | https://noesis.uis.edu.co | |
| dc.identifier.uri | https://noesis.uis.edu.co/handle/20.500.14071/37298 | |
| dc.language.iso | spa | |
| dc.publisher | Universidad Industrial de Santander | |
| dc.publisher.faculty | Facultad de Ingenierías Fisicoquímicas | |
| dc.publisher.program | Ingeniería de Petróleos | |
| dc.publisher.school | Escuela de Ingeniería de Petróleos | |
| dc.rights | http://creativecommons.org/licenses/by/4.0/ | |
| dc.rights.accessrights | info:eu-repo/semantics/openAccess | |
| dc.rights.creativecommons | Atribución-NoComercial-SinDerivadas 4.0 Internacional (CC BY-NC-ND 4.0) | |
| dc.rights.license | Attribution-NonCommercial 4.0 International (CC BY-NC 4.0) | |
| dc.rights.uri | http://creativecommons.org/licenses/by-nc/4.0 | |
| dc.subject | Tiempo Perdido Invisible | |
| dc.subject | Tiempo Productivo | |
| dc.subject | Tiempo De Referencia | |
| dc.subject.keyword | Invisible Lost Time | |
| dc.subject.keyword | Productive Time | |
| dc.subject.keyword | Reference Time | |
| dc.title | Identificación de tiempo pérdido invisible para la reducción de tiempo de construcción de pozos de un campo de Ecopetrol | |
| dc.title.english | Invisible lost time identification for the time reduction in well construction of an ecopetrol field | |
| dc.type.coar | http://purl.org/coar/version/c_b1a7d7d4d402bcce | |
| dc.type.hasversion | http://purl.org/coar/resource_type/c_7a1f | |
| dc.type.local | Tesis/Trabajo de grado - Monografía - Pregrado | |
| dspace.entity.type | Publication |
Archivos
Bloque original
1 - 3 de 3
Cargando...
- Nombre:
- Carta de autorización.pdf
- Tamaño:
- 138.16 KB
- Formato:
- Adobe Portable Document Format
Cargando...
- Nombre:
- Nota de proyecto.pdf
- Tamaño:
- 143.24 KB
- Formato:
- Adobe Portable Document Format