Asistencia tecnico-administrativa en la construccion del puente boton de leyva en la cerretera mompox-el banco

dc.contributor.advisorCruz Hernandez, Ricardo Alfredo
dc.contributor.authorHernandez Monsalve, Hector Mauricio
dc.date.accessioned2024-03-03T04:42:57Z
dc.date.available2004
dc.date.available2024-03-03T04:42:57Z
dc.date.created2004
dc.date.issued2004
dc.description.abstractEn el presente documento se muestran los pasos a seguir en cimentación de puentes, específicamente las del puente “Botón de Leyva en la carretera Mompox - El Banco”; el cual se encuentra localizado sobre el nuevo trazado que une, a la altura de la población de Guamal, la carretera que se desarrolla paralela a la margen izquierda del río, con la vía existente por la margen derecha. El puente tiene una longitud total de 498 metros y esta compuesto por una estructura principal de 260 metros de longitud (luz principal de 130 metros y dos luces laterales de 65 metros), sus accesos por viaductos con longitudes totales de 170 metros en la margen izquierda y 68 metros en la margen derecha, ancho de calzada de 8.30 metros, ancho de andenes de 1.50 metros a cada lado y ha sido diseñado para soportar camiones hasta de 40 toneladas. Antecedentes: el puente unirá los departamentos de Bolívar y Magdalena y permitirá dar continuidad al proyecto Transversal Depresión Momposina, para el establecimiento de empresas agroindustriales, las cuales darán un gran impulso a la economía de la región en términos de inversión, generando empleo y mejor nivel de vida. Reduciendo las distancias de mercado, se dinamiza el comercio, se reducen los costos y los precios de los bienes; permitiéndole a los habitantes acelerar su ritmo de crecimiento e integrarse al proceso del desarrollo del resto del país. Duración del Proyecto: El proyecto se ejecutara en un plazo de 22 meses durante los años 2004 y 2005. Localización: el puente hace parte de la carretera que va de El Banco a Mompox, cruza el río Magdalena y une los municipios de Guamal (Magdalena) y Margarita (Bolívar). Beneficios: dicha obra traerá beneficios a la región de los que se pueden resaltar los siguientes: • Generación de empleo durante el tiempo de construcción. • Disminución de los tiempos de recorrido entre los municipios de la región. • Desarrollo de actividades comerciales de bienes y servicios. • Impulso turístico en la región. • Integración regional y departamental. • Oportunidades para el desarrollo de industrias agropecuarias. • Comercialización de productos agrícolas, pecuarios, maderables, pesqueros, etc. Proceso Constructivo: los trabajos consistirán en la construcción de los accesos, el viaducto y el puente en si, incluyendo obras de drenaje, explanación, terraplenes, estructura de pavimentos, subbase granular y mezcla densa en caliente, al igual que las excavaciones, pilotaje, concretos y aceros de refuerzo.
dc.description.abstractenglishPresently document the steps are shown to continue in foundation of bridges, specifically those of the bridge "Button of Leyva in the highway Mompox – El Banco"; which is located on the new layout that unites, to the height of the population of Guamal, the highway that is developed parallel to the left riverbank of the river, with the existent road for the right riverbank. The bridge has a total longitude 498 meters and this compound for a main structure 260 meters of longitude (main light 130 meters and two lateral lights 65 meters), its accesses for viaducts with total longitudes 170 meters in the left riverbank and 68 meters in the right riverbank, wide of roadway 8.30 meters, wide of platforms 1.50 meters to each side and it has been designed to support trucks until of 40 tons. Antecedents: the bridge will unite Bolívar's departments and Magdalena and he/she will allow to give continuity to the project Traverse Depression Momposina, for the establishment of agroindustrial companies, which will give a great impulse to the economy of the region in investment terms, generating employment and better level of life. Reducing the market distances, the trade is energized, they decrease the costs and the prices of the goods; allowing the inhabitants to accelerate their rhythm of growth and to be integrated to the process of the development of the rest of the country. Duration of the Project: The project was executed in a term of 22 months during the years 2004 and 2005. Localization: the bridge makes part of the highway that goes from El Banco to Mompox, it crosses the river Magdalena and it unites the municipalities of Guamal (Magdalena) and Margarita (Bolivar). Benefits: this work will bring benefits to the region of those that the following ones can be stood out: • Employment generation during the time of construction. • Decrease of the times of journey among the municipalities of the region. • Development of commercial activities of goods and services. • I impel tourist in the region. • Regional and departmental integration. • Opportunities for the development of agricultural industries. • Commercialization of agricultural, cattle products, maderables, fishing, etc. I process Constructive: the works will consist on the construction of the accesses, the viaduct and the bridge in if, including drainage works, explanation, embankments, structure of pavements, granular subbase and dense mixture in hot, the same as the excavations, pilotage, concrete and reinforcement steels.
dc.description.degreelevelPregrado
dc.description.degreenameIngeniero Civil
dc.format.mimetypeapplication/pdf
dc.identifier.instnameUniversidad Industrial de Santander
dc.identifier.reponameUniversidad Industrial de Santander
dc.identifier.repourlhttps://noesis.uis.edu.co
dc.identifier.urihttps://noesis.uis.edu.co/handle/20.500.14071/16827
dc.language.isospa
dc.publisherUniversidad Industrial de Santander
dc.publisher.facultyFacultad de Ingenierías Fisicomecánicas
dc.publisher.programIngeniería Civil
dc.publisher.schoolEscuela de Ingeniería Civil
dc.rightshttp://creativecommons.org/licenses/by/4.0/
dc.rights.accessrightsinfo:eu-repo/semantics/openAccess
dc.rights.creativecommonsAtribución-NoComercial-SinDerivadas 4.0 Internacional (CC BY-NC-ND 4.0)
dc.rights.licenseAttribution-NonCommercial 4.0 International (CC BY-NC 4.0)
dc.rights.urihttp://creativecommons.org/licenses/by-nc/4.0
dc.subjectCimentación
dc.subjectPilotes
dc.subjectPuentes
dc.subjectHinca
dc.subjectBentoníticos
dc.subject.keywordFoundation
dc.subject.keywordSteer
dc.subject.keywordBridges
dc.subject.keywordIt sinks
dc.subject.keywordBentoníticos
dc.titleAsistencia tecnico-administrativa en la construccion del puente boton de leyva en la cerretera mompox-el banco
dc.title.englishManual of administration and control in foundation of bridges
dc.type.coarhttp://purl.org/coar/version/c_b1a7d7d4d402bcce
dc.type.hasversionhttp://purl.org/coar/resource_type/c_7a1f
dc.type.localTesis/Trabajo de grado - Monografía - Pregrado
dspace.entity.typePublication

Archivos

Bloque original

Mostrando 1 - 2 de 2
Cargando...
Miniatura
Nombre:
Documento.pdf
Tamaño:
1.93 MB
Formato:
Adobe Portable Document Format
Cargando...
Miniatura
Nombre:
Nota de proyecto.pdf
Tamaño:
361.52 KB
Formato:
Adobe Portable Document Format

VIGILADA MINEDUCACIÓN

Ordenanza No. 83 de 1.944 (junio 22)

Carácter académico: Universidad

Notificaciones judiciales: notjudiciales@uis.edu.co 

.

Código SNIES: 1204   Nit: 890.201.213-4

Línea Anticorrupción:  +57 (601) 562 9300 EXT: 3633

Línea transparente: +57 (607) 630 3031