Análisis crítico del nuevo elemento en el esquema regulatorio del suministro de energía eléctrica en Colombia : cargo por confiabilidad

dc.contributor.advisorCruz Rodriguez, Ruben Dario
dc.contributor.authorCastilla Carrascal, Sergio Alfonso
dc.date.accessioned2024-03-03T17:05:35Z
dc.date.available2008
dc.date.available2024-03-03T17:05:35Z
dc.date.created2008
dc.date.issued2008
dc.description.abstractLa Comisión de Regulación de Energía y Gas (CREG) ha venido estableciendo y perfeccionando a lo largo de los últimos años el marco regulatorio del Sector Eléctrico Colombiano -reglamentos, normas y disposiciones- con el propósito de fomentar la transparencia y competitividad del mercado de energía eléctrica en Colombia, además de proporcionar las señales requeridas para el mejoramiento continuo y desarrollo adecuado del sector. Por ésta razón la CREG estableció un nuevo mecanismo regulatorio, vigente a partir del primero de diciembre de 2006, que busca asegurar la confiabilidad en el suministro de energía eléctrica en Colombia a largo plazo, bajo condiciones de eficiencia y continuidad de abastecimiento en condiciones críticas. A este mecanismo se le denominó fiCargo por Confiabilidad. En el desarrollo del presente trabajo de grado se estudiaron y analizaron críticamente las disposiciones establecidas para la implantación del fiCargo por Confiabilidad, conceptuando sobre la interrelación y coherencia del mecanismo propuesto con la regulación vigente en el mercado. En este análisis se consideró especialmente el verificar el cumplimiento los objetivos declarados para el fiCargo por Confiabilidad con respecto a la promoción de la inversión en la actividad de generación de energía eléctrica en Colombia. El análisis cualitativo realizado, que se presenta en este documento, concluyó que efectivamente el mecanismo regulatorio propuesto puede promover la inversión en infraestructura de generación consecuentemente con los objetivos establecidos, constituyéndose en una disposición de gran pertinencia y relevancia para el Sector Eléctrico Colombiano. En este trabajo también se estableció la estructura y el esquema funcional del fiCargo por Confiabilidad identificando los componentes que lo rigen y estableciendo los procedimientos que debe seguir tanto un agente generador como un inversionistas para incorporar este mecanismo dentro de sus opciones de negocio. Esto se considera uno de los principales aportes del trabajo.
dc.description.abstractenglishThe Regulatory Commission of Energy and Gas (CREG) has been developing and refining over the past few years the regulatory framework of the Colombian electricity sectorŒregulations, rules and provisionsŒwith the purpose of promoting transparency and competitiveness in the Colombian power market, beside of providing the signals required for a continuous improvement and a proper development of the sector. For this reason, the CREG established a new regulatory mechanism, starting from December 2006, which seeks to ensure long-term reliability in the electricity supply in Colombia, that is, efficient and continuous supply under critical conditions. This regulatory mechanism was called "Reliability Charge." During this graduation work, the implementing process of the "Reliability Charge" was critically analyzed and studied, assessing its consistency and the relationship of the proposed mechanism with the current regulatory framework of the Colombian Power Market. In this analysis was specially considered the satisfaction of the proposed objectives for the fiReliability Charge regarding the promotion of the generation investment in Colombia. The qualitative analysis done, which is presented in this document, concluded that the proposed regulatory mechanism could effectively promote investment in generating infrastructure consistently with the goal of the fiReliability Charge. Then, this regulatory mechanism is seemed to be an instrument of great relevance and importance for the Colombian electricity sector development. In
dc.description.degreelevelPregrado
dc.description.degreenameIngeniero Electricista
dc.format.mimetypeapplication/pdf
dc.identifier.instnameUniversidad Industrial de Santander
dc.identifier.reponameUniversidad Industrial de Santander
dc.identifier.repourlhttps://noesis.uis.edu.co
dc.identifier.urihttps://noesis.uis.edu.co/handle/20.500.14071/21299
dc.language.isospa
dc.publisherUniversidad Industrial de Santander
dc.publisher.facultyFacultad de Ingenierías Fisicomecánicas
dc.publisher.programIngeniería Eléctrica
dc.publisher.schoolEscuela de Ingenierías Eléctrica, Electrónica y Telecomunicaciones
dc.rightshttp://creativecommons.org/licenses/by/4.0/
dc.rights.accessrightsinfo:eu-repo/semantics/openAccess
dc.rights.creativecommonsAtribución-NoComercial-SinDerivadas 4.0 Internacional (CC BY-NC-ND 4.0)
dc.rights.licenseAttribution-NonCommercial 4.0 International (CC BY-NC 4.0)
dc.rights.urihttp://creativecommons.org/licenses/by-nc/4.0
dc.subjectAnillos de Seguridad
dc.subjectCargo por Confiabilidad
dc.subjectEnergía Firme
dc.subjectGeneración de Energía Eléctrica
dc.subjectMercados de Energía
dc.subjectObligaciones
dc.subjectRegulación de Mercados de Energía
dc.subject.keywordAuctions
dc.subject.keywordFirm Energy
dc.subject.keywordContingency Mechanisms
dc.subject.keywordElectric Power Generation
dc.subject.keywordPower Markets
dc.subject.keywordObligations
dc.subject.keywordRegulation of Power Markets
dc.subject.keywordReliability Charge.
dc.titleAnálisis crítico del nuevo elemento en el esquema regulatorio del suministro de energía eléctrica en Colombia : cargo por confiabilidad
dc.title.englishCritical analysis of the new element in the regulatory scheme for the electricity supply in colombia: reliability charge*
dc.type.coarhttp://purl.org/coar/version/c_b1a7d7d4d402bcce
dc.type.hasversionhttp://purl.org/coar/resource_type/c_7a1f
dc.type.localTesis/Trabajo de grado - Monografía - Pregrado
Files
Original bundle
Now showing 1 - 2 of 2
No Thumbnail Available
Name:
Documento.pdf
Size:
2.16 MB
Format:
Adobe Portable Document Format
No Thumbnail Available
Name:
Nota de proyecto.pdf
Size:
190.22 KB
Format:
Adobe Portable Document Format